Dear all,

this is an update of our status today and our pending tasks.

Peer Review FSFE: relevant templates will be saved in Keybase for both reviewed documents (Training Plan and Platform Design Plan) asap.

O3/A2 - 01.05.-30.07.19 - Report and consultation: Peer Review from ATL done.  Dlearn pending until 31.07.19.

O2/A2 Translation of Training Course contents: all relevant partners by 30.07

O2/A2 Mother tongue videos: Greek ok. rest of videos by 31.07. by Peter/ TUD.

3rd Newsletter: sent on 26.07.2019.

Usage scenarios 2 and 3 are ready: check our page https://www.foss4smes.eu/?page_id=66 to find information.

Project Website update: Please go into file “Translations Brochure Website Newsletter” in Keybase and translate the new page marked in yellow by 14.08.19.

Feasibility study by OFE: Review was sent from Katerina. Updated version is expected by 14.08.19

O2/A1 Training Plan: Peer Review completed by OFE and FSFE. TUD to update file by 15.08.

O2/A2 Import of translations: all partners by 16.08. (Guidelines provided last time).

Multiplier events: Dlearn (and others if applicable) please send us the required supporting documents asap.

O3 consultation exercise: to be prepared by OFE and Dlearn in 6-9.09. and saved in K:\team\foss4smes\2. Implementation\Multiplier Events\Multiplier Event 4 – Brussels.

Timesheets 07-09.19: All by 20.9.

O1/A2 executive summary translation: File “FOSS4SMEs_ IO1.A2 Executive Summary”, Translations to be provided by Dlearn, FSFE, and SKUNI in K:\team\foss4smes\2. Implementation\Outputs\Output 1\A2\O1.A2. Summary translations   by 01.09.19.

O3/A1 executive summary translation: Dlearn, FSFE, ATL and SKUNI by 01.09.19.  in folder K:\team\foss4smes\2. Implementation\Outputs\Output 3\A1\Translated executive summaries

O2/A4: all partners as soon as possible in their country. Multiplier events. Results of our O2/A4 should be ready before our meeting in Brussels.

4th transnational meeting: partners can enter travel details here: team/foss4smes/5. Meetings/4. Brussels

TU Dublin Invoice: TUD to reply ASAP. payment still pending.

Certificates of participation – Dublin Meet.: Pending from TUD. ASAP.

Stakeholders Matrix: SKUNI[KT1] , TUD[KT2]  should insert 25 entries in the table. ASAP.


 [KT1]to
be able to provide contacts for the stakeholders matrix) we stress the
importance of providing content for use under usage scenario 3

 [KT2]We were working on this in conjunction with our multiplier event so I will get a list from our internal admin



Thank you all for our cooperation. I will be away until 20.08.19, but please feel free to contact me on urgent matters.

Best,
Katerina

--

 

atlantis-logo-for-signatures

Katerina Tsinari

EU Projects consultant

Αntoni Tritsi 21, 570 01 Thessaloniki

T:

2310 233 266

Email:

tsinari@abe.gr

URL:

www.abe.gr

Skype:

 tsinarikaterina@hotmail.de